GSR038 - Single Transformer Offshore AC Substations
This modification is proposed to assess the restriction in Clause 7.7.1.1 that effectively requires two offshore AC transformers for grid entry point capacities of 90 MW or more.
Modification status:
Current
- Proposal Raised
Last updated:
10 March 2026
Code administration contact: [email protected]
This modification is expected to have a: High impact on Offshore Transmission Owners (OFTOs) and Offshore Generators and a Medium impact on NESO
Governance Route: Standard Governance modification to proceed to Code Administrator Consultation
Code modification proposed by:
Slawomir Kurek