CMP465: Construction Progression Milestones (M5-M8) Neutrality
This modification aims to deal with the extension given on the G2tWQ Connections offers until 2026 (from the end of 2025) and give affected Users the option to be placed back to the position they would have been (in terms of M5-M8 milestones only) had this extension not occurred.
Modification status:
Current
- Proposal Raised
Last updated:
21 November 2025
Code Administrator Contact: [email protected]
Governance Route: Urgent modification to proceed under a timetable agreed by the Authority (with an Authority decision)
Impacts: Low impact on Generators and Demand
Code modification proposed by:
Garth Graham